JHR NEWS, January 2015

On the Jules Horowitz research reactor construction was successfully completed assembly of modules W+1 which was handed over by the general contractor (RAREZ – BEC). The contractor can now finish steel reinforcement and final concreting of the building.

Gallery:

Pictures description:
Fig. 01. 10 W+1 Module construction – a wall of the large hot cell ECD
Fig. 02+03. M10 Module
Fig. 04. Reactor dome concreting
Fig. 05. Modules W+1 of the last floor of the large hot cells – general view
Fig. 06. Sliding door frame welding
Fig. 07. Assembly team